With explosive growth for Fort Mill and Tega Cay comes infrastructure challenges. ?Needed road upgrades is one of the most talked about subjects in our area. In York County D1?Councilman Michael Johnson’s August newsletter, he posted an update on Pennies For Progress road construction projects in our area. ?Here is Michael’s road update report:
SC Highway 160/Gold Hill (SCDOT Project) – $10,586,100
- Will create two (2) dedicated left turn lanes in each direction and widen intersection
- Construction work has begun
- Right of Way acquisition is ongoing, 10 possible condemnations to be required
- Completion December 2016
Hubert Graham Way (Pennies for Progress 2 Project) – $10,057,613
- Will create an alternate way to Hwy 160 closer to entrance of Tega Cay
- Construction work has begun
- Stonecrest Blvd opened to traffic on June 11th
- Completion Summer 2017
SC Highway 160/Zoar Road (Pennies for Progress 3 Project) – $10,500,000
- Will create left turn lane on to Zoar Road and four (4) lanes to NC line
- Right of Way acquisition to begin Fall?2016
- Anticipate construction to begin Fall 2017, Completion Summer 2019
Gold Hill/I-77 (SCDOT Project) – $12,449,811
- Will create a diverging diamond interchange to improve traffic flow
- Federal Highways has given approval, 70% Plans approved
- Right of way acquisition has begun
- Anticipate construction to begin Fall 2017, Completion Fall 2019
US Highway 21/SC Highway 51 (Pennies for Progress 3 Project) – $32,000,000
- Will 5-lane Hwy 21 and Hwy 51 from Springfield Parkway intersection to NC border
- Right of way plans submitted to SCDOT on July 30th
- Right of Way acquisition planned for late 2016/early 2017
- Anticipate construction to begin 2018, Completion Spring/Summer 2020
Potential Exchange Projects with SCTIB (SC State Infrastructure Bank) – $215,860,000
- Improvements to I-77 and Carowinds Boulevard
- Improvements to I-77 and Gold Hill Road (to include additional improvements beyond diverging diamond)
- Improvements to I-77 and Hwy 160
- Improvements to I-77 and Sutton Road
- Improvements to I-77 and Celanese Road
- York County has submitted an application to the SCTIB Board for approval of the intersections listed above.? RFATS has already approved funds to be used for engineering work
- Anticipate construction to begin 2020, Completion 2021/2022 (if funding approved by SCTIB)
- SCTIB board is meeting in September to discuss our application